The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Importing a sprint value via csv

Patrick Windsor
May 4, 2015

Hello, I am trying to import a numbers of issues and the value I have for the sprint will not come in. My sprint is labeled "Iteration 9", "iteration 10", etc. In the csv I entered "iteration 9" and it would not accept it I also tried "9", but it came in as a different value. 

Is there a way to get the sprint value in?

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

1 vote
Andre Borzzatto
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
May 4, 2015

Hi Patrick,

It shouldn't be possible to map the Sprint custom field in the CSV import, although you can select the Sprint field to be mapped, the value won't be sticking into JIRA, unfortunately.

We had a user that created a suggestion to enable this field mapping, however, JIRA Agile team mentioned that they do not plan to import this feature any time soon.

Thanks and I hope it helps!

TAGS
AUG Leaders