The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 
  • Community
  • Q&A
  • Jira
  • Questions
  • If subtasks are planned between teams there should be possibility to see them on planning mode of Scrum boards.

If subtasks are planned between teams there should be possibility to see them on planning mode of Scrum boards.

Madura Rodrigo
November 24, 2016

We have Possibility to have multiple sub tasks in  on story which should be handled from multiple teams. And we need to show corresponding sub-task in relevant scrum board. And planning mode to plan them.

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
November 24, 2016

Er, it's nonsense to plan sub-tasks outside their story, so they don't appear in planning.

Madura Rodrigo
November 24, 2016

I agree on Story concept. But Scenario like multiple teams work in one issue, they should have separate sub tasks. And they need to plan them under their time line. Main issue owner should have track on sub tasks. Is JIRA agile support only one team one issue manner?

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
November 24, 2016

Planning is for prioritising and deciding which stories go into a sprint.  Subtasks are part of stories, so they follow their story into a sprint.

If you have multiple teams, that's fine, and sub-tasks are a good way to break up stories into pieces that can go out to different people.  But your teams are working on one story, so they should be in the same scrum.

Madura Rodrigo
November 27, 2016

As a alternative for my requirement, I can use Epic with issue type. So I can link set of issues to one epic. Then we can handle issues between teams. Is there possibility to inherit epic type?