The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 
  • Community
  • Q&A
  • Jira
  • Questions
  • If I move my jira issues from one project to another what happens for closed sprints and issues?

If I move my jira issues from one project to another what happens for closed sprints and issues?

Yogesh Vinayakrao Kulkarni
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 14, 2024

Hi Team,

I have one scenario, I want to move all my jira issues from one project to another. After moving what happened with closed sprints and user stories? What would be the status of them on new project?

 

Regards,

Yogesh K

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Marc -Devoteam-
Community Champion
March 15, 2024

HI @Yogesh Vinayakrao Kulkarni 

On moving issues to another project, you will be asked what to do with the status if the workflow(s) differ.

You sprint information will be carried over as well, but the reporting can differ on information.

This concerns the burn up and burn down and the velocity reporting on the target project will be impacted.

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
March 15, 2024

This is a bit of a complicated one, there's two bits to think about.

The issue will retain the data that matters to the sprint - specifically the estimates, status, and that it was included in an active sprint.  (If you search for "sprint = X" you will find the issue, even if it has moved to a different project)

But.  If the issue no longer meets the criteria to be included on the board the sprint was created from or now has a status that is not mapped or has changed whether it is in the done or any not-done column, it will look like it was removed from the sprint.  Your sprint reports will show this.