The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 
  • Community
  • Q&A
  • Jira
  • Questions
  • I need a way to experiment without affecting the live plan - what’s the best way to do that in Jira?

I need a way to experiment without affecting the live plan - what’s the best way to do that in Jira?

sareha163
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 14, 2025

Hi, I'm juggling multiple project plans in Jira, and it's getting overwhelming. Sometimes, I want to test different timelines, shift resources around, or see what happens if we adjust priorities, but I don’t want to mess up the actual project tracking. I need a way to experiment without affecting the live plan - what’s the best way to do that in Jira? Is that even possible?

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

6 votes
Answer accepted
Sahir Maharaj
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
March 14, 2025

Hi @sareha163

I’ve been in that exact situation before, and Jira’s Advanced Roadmaps are great. The best way to experiment without affecting your actual project data is by using scenarios. (Think of them as sandbox versions of your project)

What I usually do is go into my plan, open the Scenario dropdown, and create a new one with a unique name and color (trust me, the color helps when you’re switching between them!).

From there, I start making adjustments, maybe increasing team velocity, moving a deadline forward, or testing what happens if we add more work.

The beauty of this is that all these changes stay inside the scenario until I decide to apply them to the live plan.

If you’re managing multiple project scenarios, this is hands down the best way to stay flexible without breaking anything

Here’s a quick tutorial that I thought will be useful: https://youtu.be/ots-jOtvtqk

Hope this helps! :)