I closed a sprint without moving all the tasks to done; as a result a new sprint was created

Edith Orozco
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 1, 2022

I'm still learning Jira, and I made the mistake of closing the Sprint without moving all the tasks from the "ready for the client" column to the "complete" column.

As a result, a new Sprint with all the tasks was automatically created. How can I

a) Marked all those tasks as done

b) Eliminate this "new" Sprint

It would be even better if I could reopen the Sprint where I made a mistake and correct it.

1 answer

1 accepted

1 vote
Answer accepted
Mohamed Benziane
Community Champion
March 1, 2022

Hi @Edith Orozco 

Welcome to the community

You can find all the information you need here

https://support.atlassian.com/jira-software-cloud/docs/reopen-a-sprint/

Edith Orozco
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 3, 2022

Thank you very much! Your answer helped me to solve the issue!