How would I create a PMO grade project risk register in Jira?

Donna Dalton
August 1, 2017

I manage agile dev projects using Jira. Sometimes using SCRUM other Kanban.

In my organisation I have to work within a PMO framework. To fulfil the PMO requirements I need to have a robust risk register. Is there a way I can record and track and report on project risks using Jira?

1 answer

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
August 1, 2017

There's broadly two approaches to a risk register in JIRA.  Neither of them are right or wrong, the choice depends entirely on how you want to work.  (You can use a mix both if it's going to help you)

  • Per project - Create a "risk" issue type and add it to projects
    • Advantages:  a strongly project-focussed set of risks and good visibility for the people using the project
    • Disadvantages:  a lot of teams don't see risks as direct items that they can deal with, so they can't be planned, estimated or included. They're usually broad things that can't really fit into a development cycle.
  • Global - Create a "risk" project and log risks in there
    • Advantages:  everything in one place, and your users won't have them in the way of other stuff
    • Disadvantages: that there's only a weak link to a project and people who aren't directly focussed on them won't pay attention to them.

In both cases, the risks can (and should!) have their own workflows and fields etc.

Finally, I would strongly recommend a look in the marketplace for risks.  There's a lot of add-ons that can help, and even when the add-ons themselves might not be what you need, their vendors have some very good writeups on doing risks in general.

Donna Dalton
August 1, 2017

Thank you so much. That is really helpful.