I would like to get the list of CRs moved from "In Implementation" to "Implementation Done" state from 01-June-2016 to 26-Nov-2016.
Current state of the CRs can be anything in this case.
Can you please help?
Thanks,
Giridharan
You can do something like this:
status changed from "In Implementation" to "Implementation Done" after "06/01/2016" before "11/26/2016"