How to show linked issues connected to subtask on jira board

Maciej Kotlarz
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 23, 2023

Hi,

I am trying to modifi our team board regarding to our needs. W have got:
1) Stories - no story points
2) [Frontend] Task - 3 story points
3) [Backend] Task - 3 story points

We are using stories just to track our work, no story points are assigned to story. Story Points are connected to specyfic tasks. See above.

Both of tasks are the same task, but are divided to FE and BE part. Exaple:
1) [Story] Agency Margin 
2) [BE] Add Agency service type - 2 SP
3) [FE] Add Agency margin field - 5 SP

Analogously as with subtasks and story I would like to see linked issues under story on board?

Is it possible to create something like this? Do not hesitate to ask more questions in case of wrong explanation :)

1 answer

0 votes
Trudy Claspill
Community Champion
February 26, 2023

Hello @Maciej Kotlarz 

Welcome to the Atlassian community.

No, it is not possible to showed linked issues on a board in the same manner that subtasks are shown "under" their parent issue. An issue can be linked to any number of other issues, whereas a subtask can have only 1 parent, so how would Jira decide under which Story the Task should be displayed?