The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

How to set original estimate (time) to Issue?

Evgeniy Nechayev
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 11, 2016

I do not want to use Scrum, I do not want to use Agile. I want to set Time Estimation for issue and using Time tracking only. 

How to add Original Estimation field to Issue creation screen?

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

1 vote
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
November 11, 2016

Add the field called "time tracking" to the issue create screen (you can find it by working down through the project's "issue type screen scheme")

Kamal Kailasa Babu
April 20, 2020

how to bring this "time trcking" field?