How to say planned start planned end for 1 hour every night

Mike Hang TR May 16, 2023

Consider I have a project keeping track of change requests.

I have someone who needs to make a change across several of our buildings that will take several nights to accomplish. 

Creating an individual 1 ticket per night cannot work because the description of work to be done on day 2 is determined on how far he got on day 1.

So, I want to approve 1 ticket that allows him for example to work Monday - Thursday for 1 hour a night. Right now, it looks like Monday 10 PM - Thursday 11 PM.

How have others overcome this hurdle?

 

1 answer

0 votes
Brant Schroeder
Community Champion
September 2, 2023

@Mike Hang TR Why don't you have the parent issue and then sub-tasks for each of the days that need work done.  then you can approve the parent and he can keep track of his work each night.

Brant Schroeder
Community Champion
March 6, 2024

@Mike Hang TR If this was helpful can you accept it?