I would like to reinitialize the temporal tracking to 0,
The estimated time and the remaining time for a task.
I haven't found the way to do that. Is someone able to help me ?
The estimated time and remaining time fields can be edited directly (assuming you have permissions) and set to zero manually.
To reset the "temporal tracking" you'd have to go into the Worklog Entries for the issue and delete them. Again, you'll need the appropriate permissions to do this. The ability to delete Worklog Entries (even your own) can be restricted. In that case, you'll need to contact your Jira Admin for help.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.