The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

How to measure Unassigned time and Open time and record them into Log Work?

Hisamitsu Koga
Contributor
October 18, 2016

I want to measure Unassigned time: Issue Creation time  - Issue Assigned time and Open time: Issue Creation time - Start Progress automatically and record thme into Log Work? Is it possible to do this? If yes, how can we do it?

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

Post a new question

0 votes
Bharath Kumar
October 18, 2016

Hi Hisamitsu,

You can use the add-on Time in Status to track time each and every status and in between transitions. Hope this will help you.

Hisamitsu Koga
Contributor
October 19, 2016

Hi Bharath,

 

Thank you for your reply. Yes, Time in Status add-on is very useful.