We're planning to go with Advanced road map (AR) for high-level planning, and general visibility. However, we've noticed that AR tends to allocate workload for any given task as 5 days per week, and remaining days goes into last left week(s).
Hence, how can we make it split equally across assigned weeks (by dragging bar on timeline)? E.g. assume our weekly capacity is 25 days (5 people), and if we have task with estimate 18 day work, we should be able to both assign for 6 weeks (3 days a week), or assign onto 2 weeks (9 days a week).