Hi,
How to import new sub-task in CSV to existing parents in jira? I want to match tasks(parents) that already exists in jira with sub-task (childs) which are new. What fields do I need to fill in in csv to make such a connection?
Hi Sabina - Welcome to the Atlassian Community!
Just add a column to your CSV for Parent. Then put the issue key of the existing Parent into that column for the sub-task. For example, ABC-123
Summary Parent
Sub-task 1 ABC-123
Sub-task 2 ABC-123
Sub-task 3 ABC-123
You are welcome
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Welcome to great meetings, with less work. Automatically record, summarize, and share instant recaps of your meetings with Loom AI.
Learn moreOnline forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.