The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results forĀ 
Search instead forĀ 
Did you mean:Ā 

How to handle two dependent Issues, but unique from a workflow perspective

Darren
Contributor
February 25, 2015

Two Scrum tasks.

Both in the same project

Both dependent on each other (i.e. both must complete within the Sprint)

But both have completely different work flows.

Should they reside in different Jira projects?

Or, perhaps, one should be given a different Issue Type to map it to its unique Workflow?


Although Scrum suggests the cross-functional team, in reality there is an SME team focussed on specific infrastructure tasks (such as building out new AWS environments) that the application feature team will never touch, and vice versa.

My initial thoughts are:

  • Keep them in one JIRA project (as its all contained in one Sprint) and rely on the tasking out of an individual Product Backlog Item, when produce sub-tasks, to assign the work;  but can there be different types of sub-task each with its own workflow?

 

JIRA version is 5.1 / JIRA Agile is being used.

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

Post a new question

1 vote
Answer accepted
Jobin Kuruvilla [Adaptavist]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
February 25, 2015

Yes, they can be of different issue types or different subtask types and they can have different workflows. Both can be in the same project and on the same board.