The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results forĀ 
Search instead forĀ 
Did you mean:Ā 

How to enable 'Estimation' in scrum board configuration?

Harsha Surendra Kumar
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 25, 2022

We have to track the time spent v/s remaining estimate in burn down chart and my understanding is that we have to enable Time Tracking in Estimation configuration and select Time Tracking to "Remaining Estimate and Time Spent".

To enable the above, we're not finding 'Estimation' option in scrum board configuration. Any suggestions how to enable 'Estimation' option ? 

2 answers

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

1 vote
Answer accepted
Walter Buggenhout
Community Champion
October 25, 2022

Hi @Harsha Surendra Kumar and welcome to the Community!

If your board is linked to a company managed project, then navigate to Board Settings (from the ... button in the top right corner of your board) and then navigate to the Estimation page:

Screenshot 2022-10-25 at 15.51.47.png

In a team managed project, navigate to Project Settings > Features and select the appropriate option from the Estimation panel:

Screenshot 2022-10-25 at 15.53.58.png

Hope this helps!

Gleb
December 7, 2022

It works for my team management project. But it works only when I completely remove the existing project and create a new one. Before removing there is no Estimation feature in Project Settings > Features list. 

Trudy P Claspill
Community Champion
December 7, 2022

Hello @mome 

Are you working with a Software, Service, or Business project when the option does not appear?

Can you provide a full screen image that includes the navigation pane on the left for an instance where you don't see the option?

0 votes
Trudy P Claspill
Community Champion
October 25, 2022

@Walter Buggenhout 's answer applies to a Company Managed project.

If you are using a Team Managed project you would need to go to Project Settings > Features.