We have a number of issues that were addressed in a previous sprint, but the sprint was closed without moving them to the done column, so they are showing up in our new sprint. They've been moved to done, but this is not correct ( as they are not completed in this sprint, but in our previous one ).
We want to be able to go back and mark these tasks as completed in the previous sprint, but I do not see how to do this.
Can you please advise how I can do this?
Hello David,
have you tried just edit issues and delete value from Sprint field? Then only previous sprint should be stated in the Sprint field.
Cheers,
Milos
Hi Milos,
I believe this would take the issue out of our current sprint, but looking at the previous sprint report, all of these issues will still show up as incomplete.
If possible, we want to be able to have these issues be completed in the previous sprint.
Thanks,
David
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.