How to block status change of a task, if its dependent on another task

Soni Jha
July 31, 2017

Task 2 is dependent on Task 1. I have created a dependency, but still I am able to mark Task2 in progress though Task 1 is still not complete. How to enable this?

1 answer

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
July 31, 2017

You will need a little bit of code to put in a "condition" - it should be able to look at Task1 and return "false" if it is incomplete, which will remove the option to use the transition on task2.

There are a load of add-ons in the marketplace that can provide that code, or a way to implement your own version of it.

Soni Jha
August 3, 2017

Thanks Nic. It will be helpful if you can share some links for add-ons

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
August 3, 2017

The marketplace is the best place to look.