The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

How to automatically change Time Tracking when an Original Estimate is changed?

Martin Junek
January 26, 2023

Hi! I am in Jira Software Cloud. When I change an "Original Estimate", remaining time in "Time Tracking" field does not change. Logged time works well, but remaining time is still on the original remaining time. Is there any possibility to adjust it? Thank you:) 

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Answer accepted
Ashish Bijlwan
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
January 26, 2023

Hi @Martin Junek 

Welcome to Atlassian Community!

The Original Estimate is a static value. Once set, it sets the baseline Time Remaining value.

Ideally you should be setting Original Estimate before any time is logged against the issue then only Remaining Time will automatically update.

Once you logged  the time against the issue and after that you change or update the Original Estimate, Remaining Time will not update automatically, you have to explicitly update the Time Remaining to a specific value.

To do so click on the Time Tracking where you Logged and Remaining Time is visible

image.png

and it will open the Time Tracking window, where you can edit the Time remaining accordingly.

image.png

 

Thank you,
Ashish

Martin Junek
January 26, 2023

Hello Ashish, 
thanks a lot for your answer. :) I was looking in the documentations all around and I did not see any solution so I thought that I have to do it manually, but I had some hope. 
Have a nice day!

Like Ashish Bijlwan likes this
Darcy M
March 14, 2025

Hello @Ashish Bijlwan I am also having the same issue but the thing is, we don't have any logged work yet. I have tried updating the original estimate from 6 to 3 but it doesn't update. Is there any specific explanation about this?

Ashish Bijlwan
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
March 17, 2025

Hi @Darcy M 

Could you please share the steps and the screenshot.  Because the issue you mentioned should not happen. 

 

Regards,