Hi,

I am using Jira v.12.0

I have a project that use an "Estimated Hours" field. I want to hide the "Estimated Hours" field on this project and instead i want to use the Jira default fields  "Original Estimate" & "Remaining Estimate".

Any how to guide? i have searched on google but unfortunately i wasn't able to find anything.

Thank you,
Drilon

1 answer

2 votes
Pete Singleton
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 7, 2019

These two fields can be added to a screen by adding the system field named "Time Tracking".

Also note that Time Tracking needs to be enabled for the project.

Full details here: https://confluence.atlassian.com/adminjiraserver083/configuring-time-tracking-976768531.html