Hi everyone,
In 1 epic, I can have severals tasks and i would like to add, for each of them a roadmap bar but i don't know how to do it, could you please help me ?
Hi @[deleted] and welcome to the Community!
Assuming that your roadmap is in a Company Managed project, navigate to Board Settings from the board view in your project. Navigate to the Roadmap page in settings and set the toggle for child level issue scheduling to on:
After that, you should be able to add roadmap bars to your tasks on the roadmap.
Hope this helps!
Hi @[deleted]
You can activate this in Team-managed Projects also
Ste
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks a lot Walter! It works now!