The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

How to add roadmap bar to tasks?

Deleted user
January 12, 2023

Hi everyone, 

 

In 1 epic, I can have severals tasks and i would like to add, for each of them a roadmap bar but i don't know how to do it, could you please help me ? 

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

1 vote
Walter Buggenhout
Community Champion
January 12, 2023

Hi @[deleted] and welcome to the Community!

Assuming that your roadmap is in a Company Managed project, navigate to Board Settings from the board view in your project. Navigate to the Roadmap page in settings and set the toggle for child level issue scheduling to on:

Screenshot 2023-01-12 at 15.38.17.png

After that, you should be able to add roadmap bars to your tasks on the roadmap.

Hope this helps!

Ste Wright
Community Champion
January 12, 2023

Hi @[deleted] 

You can activate this in Team-managed Projects also

  1. Go to the Roadmap
  2. In the top-right, select the breadcrumbs (3-dots icon)
  3. From the drop-down, select Configure Roadmap
  4. Ensure the Child Level Issue Scheduling option is toggled to ON

Ste

Deleted user
January 12, 2023

Thanks a lot Walter! It works now!