Hi, 

I'd like to be able to edit the estimate (agile story point) in the create/edit incident view. I'm not talking about the "tracking time" fields. I'm talking about the story points "estimate" field that shows up in the preview.

Also, I mean when the story is still in the backlog or in a non-started sprint. 

thanks! 

 

1 answer

1 accepted

0 votes
Answer accepted
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
June 19, 2017

Just put the "story points" field on the create and edit screens.  (Assuming you're using that field for it)

pblauer
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
June 19, 2017

my bad.. i'd tried this but it wasn't working.. now it does work.. don't know why.. may be I tried to configure in a different screen.. thanks