Hi,
I'd like to be able to edit the estimate (agile story point) in the create/edit incident view. I'm not talking about the "tracking time" fields. I'm talking about the story points "estimate" field that shows up in the preview.
Also, I mean when the story is still in the backlog or in a non-started sprint.
thanks!
Just put the "story points" field on the create and edit screens. (Assuming you're using that field for it)
my bad.. i'd tried this but it wasn't working.. now it does work.. don't know why.. may be I tried to configure in a different screen.. thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.