Is there a way to add a ticket to a sprint that is already completed?
Hello @Jean Nguyen
Good day! Welcome to Atlassian Community!
The Sprint field only displays Active Sprint & Future Sprints in the dropdown. To add an issue to already closed Sprint, you can either reopen the Sprint and add the issues or perform a Bulk edit operation to update the Change Sprint field with the Sprint ID of the closed Sprint. However, both actions will impact the Sprint reporting.
I hope that helps!
Thanks
Hello @Jean Nguyen
You need to reopen the sprint to add an issue to it.
Why are you needing to add an item to a completed sprint? If the item was worked on during the sprint why wasn't it added to the sprint while the sprint was active?