The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

How to add Due Date (is not visible) in the backlog and Sprint desk?

e_shakalov
August 24, 2021

work in jira cloud with administrator rights (a project managed by a company)2021-08-24_13-41-12.png2021-08-24_13-37-01.png

the photo shows an example of how it should turn out

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

Post a new question

1 vote
Answer accepted
Jack Brickey
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
August 24, 2021

With CMP projects you can add up to 3 fields on a given card. This applies to sprint/Kanban boards and backlogs. Board settings > card layout

e_shakalov
August 24, 2021

Thank you, I did it, the deadlines were displayed in the Backlog and Sprint, but how do I make them highlight when the deadlines are lit?2021-08-24_16-27-03.png

Jack Brickey
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
August 24, 2021

There isn’t a way to highlight the due date. However you could consider using the card color feature to say give it a red bar if the due date is near. Please play with this idea and if you run into issues let me know.