The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

How to Inactive sprint if EndDate is past date?

Sweety
June 27, 2019

We have started one sprint and it was now past EndDate, So now we are unable to end that sprint.. How can we remove this print from the Active sprint list?

2 answers

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Jack Brickey
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
June 27, 2019

Are you saying you cannot “stop” the sprint. That should not be the case.

Sweety
December 15, 2020

..

Sweety
December 15, 2020

 

 

Sweety
December 15, 2020

..

0 votes
PVS
Banned
June 27, 2019

Hi @Sweety 

 

 

If yow want Delete  that Sprint sample.PNG

if you want move the issues follow the link 

https://community.atlassian.com/t5/Jira-Software-questions/Closing-sprint-and-issues-move/qaq-p/237402