Suppose team deliver sprint one to client. Now team working on sprint two. Client report one bug of sprint one in between. So at this stage what should I do? As Scrum always suggest do not change sprint plan unless it create big impact on business value. But here client nature is like that - we already report bug to you still you not fixed after delivering of sprint two. So what approach should we use?
Most stick to Scrum - the bug is a new story, so it goes into the backlog (and is usually ranked very high, so it goes into the next sprint).