Suppose team deliver sprint one to client. Now team working on sprint two. Client report one bug of sprint one in between. So at this stage what should I do? As Scrum always suggest do not change sprint plan unless it create big impact on business value. But here client nature is like that - we already report bug to you still you not fixed after delivering of sprint two. So what approach should we use?
Community moderators have prevented the ability to post new answers.
Most stick to Scrum - the bug is a new story, so it goes into the backlog (and is usually ranked very high, so it goes into the next sprint).