  • How does Jira Portfolio calculate duration, minimum work package size doesn't seems to be considered

How does Jira Portfolio calculate duration, minimum work package size doesn't seems to be considered

Nicolas Gendron
April 10, 2017

A ridiculously small items in my portfolio (180 story points) takes, in length, about half of an items with 2160 story points.

I only have 1 team defined and no releases exist as of now.

I tried to play with the "Minimum Work Package Size" parameter and put it at 60 (so, 3 sprints to do the small items) and nothing seems to change, even recalculating does nothing.

Any ideas? 

 

1 answer

0 votes
Nicolas Gendron
April 11, 2017

I still don't understand why, but it seems that when a high level item in the portfolio has child issues and the other not, this has an influence.