Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

How does Jira Plans pull in data from the Project link?

Joni Johnson
Contributor
November 6, 2025

We have a plan setup that pulls data from the Jira Project. The work item rules are to not show items that are done 30 days or older. Viewing the plan on 11/5/25 and 11/6/26 there is one item in the project that was closed on 11/5/25 and it does not show on the roadmap. Since we are excluding items closed 30 days or later, I would expect it to show. We don't have any specific work items excluded by user or releases. 

Anyone have ideas on what is occurring or where I need to look to see if there's a setting I am missing?

Thanks.

1 answer

0 votes
Karthik Chintapalli November 7, 2025

Hi @Joni Johnson 

Advanced Roadmaps does not always calculate age based on the Resolved/Done Date
Jira Plans uses Completed Date not Done Date and also check for any subtasks are there

 

Thank you

Karthik

Joni Johnson
Contributor
November 7, 2025

@Karthik Chintapalli Thank you for the response.  Is there a way to view or export the completed date? I tried JQL for the key in question and complete wasn't a column selection. Can you clarify what is meant by check any subtasks are there? 

Karthik Chintapalli November 10, 2025

Hi @Joni Johnson 

 How to view/export the Completed Date
Advanced Roadmaps’ Completed Date is not an Issue field in Jira and cannot be added as a column or exported through JQL.
It is an internal calculation used only inside Plans based on:

Resolution date

Status transition history

Subtask completion

Parent/child roll-ups

There is no JQL field, no column selector, and no direct API field.

To infer it manually:
Open the issue → History → check the timestamp when it moved into a Done status, and ensure all subtasks reached Done. Plans may shift the completed date forward if subtasks ended later.

 

and coming to subtask

 

In Plans, a parent item is not considered complete until all subtasks are complete. Example:

Parent Story moved to Done on Nov 5

One subtask finished on Nov 12

Plans considers the Story’s Completed Date = Nov 12, not Nov 5.
If that moved it outside the 30-day range, the Story disappears from the Plan.

This behaviour applies to:

Epic → Stories

Story → Subtasks


Let me know if you have any questions

 

Thank you 

Karthik

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
TAGS
AUG Leaders

Atlassian Community Events