We have a plan setup that pulls data from the Jira Project. The work item rules are to not show items that are done 30 days or older. Viewing the plan on 11/5/25 and 11/6/26 there is one item in the project that was closed on 11/5/25 and it does not show on the roadmap. Since we are excluding items closed 30 days or later, I would expect it to show. We don't have any specific work items excluded by user or releases.
Anyone have ideas on what is occurring or where I need to look to see if there's a setting I am missing?
Thanks.
Hi @Joni Johnson
Advanced Roadmaps does not always calculate age based on the Resolved/Done Date
Jira Plans uses Completed Date not Done Date and also check for any subtasks are there
Thank you
Karthik
@Karthik Chintapalli Thank you for the response. Is there a way to view or export the completed date? I tried JQL for the key in question and complete wasn't a column selection. Can you clarify what is meant by check any subtasks are there?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
How to view/export the Completed Date
Advanced Roadmaps’ Completed Date is not an Issue field in Jira and cannot be added as a column or exported through JQL.
It is an internal calculation used only inside Plans based on:
Resolution date
Status transition history
Subtask completion
Parent/child roll-ups
There is no JQL field, no column selector, and no direct API field.
To infer it manually:
Open the issue → History → check the timestamp when it moved into a Done status, and ensure all subtasks reached Done. Plans may shift the completed date forward if subtasks ended later.
and coming to subtask
In Plans, a parent item is not considered complete until all subtasks are complete. Example:
Parent Story moved to Done on Nov 5
One subtask finished on Nov 12
Plans considers the Story’s Completed Date = Nov 12, not Nov 5.
If that moved it outside the 30-day range, the Story disappears from the Plan.
This behaviour applies to:
Epic → Stories
Story → Subtasks
Let me know if you have any questions
Thank you
Karthik
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.