Does Jira expect the team members to keep switching between Backlog and Active sprint views?
I would say we do need a Rank field (a number input) in addition to Priority. Ranking only by manual drag-and-drop is not sufficient.
Any workarounds?
We use JIRA 7.10 server version.
In the Project Configuration: General and Filter screen, ensure the Filter option 'Ranking' says 'Using Rank'.
The rank of the Unassigned issues in the Active Sprints screen should be the same (*for those issues only*) as in the Backlog screen.