The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

How do I enable the Kanban backlog?

Avrohom Yisroel Silver
Contributor
July 12, 2023

I have set up a project using the team-based Kanban template, and have added epics and issues.

I would like to enable the backlog, as I want to start organising the issues into releases.

I saw this article, however it doesn't relate to what I see on the screen.

I clicked the ... link, which took me to the settings, with the "Columns and statuses" link selected. According to that article, "The Column settings page displays, with the Kanban Backlog as the leftmost column." I don't see a Kanban column...

Screenshot 2023-07-12 210934.png

Anyone any idea what I'm doing wrong? How do I enable the backlog?

Thanks

2 answers

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

1 vote
Answer accepted
Avrohom Yisroel Silver
Contributor
July 12, 2023

Duh, silly me. I have a team-based project, so needed to go to the project settings to enable the backlog

If there is anyone there with the authority to do so, please delete this question

Jehan Bhathena
Community Champion
July 13, 2023

Hi @Avrohom Yisroel Silver ,

Please mark one of the Answers as Accepted,  there isn't an option to delete a Community question :-P

I would suggest marking your own answer as Accepted if this solved your main question.

Avrohom Yisroel Silver
Contributor
July 13, 2023

OK, thanks

2 votes
Laurie Sciutti
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
July 12, 2023

Hello @Avrohom Yisroel Silver ~ in order to enable the Kanban backlog, you need to drag and drop one of the Status cards to the Unassigned statuses section (the left portion of your screen shot).  This is typically the initial create status -- "To Do" in your case.  So click the "To Do" status card currently mapped to your "To Do" column and drag it to the Unassigned statuses section.  Then click the "back to board" button and you should see the backlog link in the left nav.