The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

How do I display my entire sprint on my timeline?

McKenna Hogan
Contributor
June 6, 2024

Hello,

I noticed that on my scrum board timeline, it only shows issues that are under an epic. Is there a way to show issues that aren't connected to any epic?

Thanks!

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

1 vote
Answer accepted
Trudy P Claspill
Community Champion
June 6, 2024

Hello @McKenna Hogan 

With the Standard product plan the answer is no. The Timeline feature offers just basic functionality and part of that is displaying only issues that are children of Epics. There is a change request about this to which you can add your vote:

https://jira.atlassian.com/browse/JSWCLOUD-25744

The Advanced Roadmaps Plans functionality in the Premium/Enterprise product plans offers more robust functionality if you are willing to upgrade.

Otherwise you would need to look at a third party app.

 