How do I configure Create SubTask screen?

Lana Decker
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 6, 2013

I have 2 types of subtasks - Test tasks and Development tasks.

All I want to see on them is "Assignee", "Acceptance criteria", "Description", "Summary" and hour estimates fields (Log Work). How do i do that?

I was thinking to use " Add Issue Type Screen Scheme " but I can map it to Issue types, not sub tasks...

1 answer

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 6, 2013

Actually, yes, you do use "issue type screen schemes". The screen schemes are there to say "use screen X for purpose Y when using issue type Z". They don't care whether an issue type is a top level issue or a subtask.

When you add a new screen scheme to an issue type screen scheme, you'll find it simply lists all the issue types you have in your system.