When adding a new issue I can select the sprint to add it too. We are currently working sprint 3, and have a couple of future sprints planning up. However sprint 1 is still hanging around as acitive.
None of the Agile boards show sprint 1 just sprint 3... how can i find Sprint 1 and close it?
2015-02-13 14_12_14-Create Issue - JIRA.png
Search for issues with that sprint in the issue navigator and see if there are any issues in that Sprint. If you find one, create a board that will include the issue and then close the sprint from that board ![]()
It seems that the sprint has no issues in it, and on the board it says "no active sprint"
JQL (sprint = 3) Maybe if I create a blank issue in the sprint it will appear and let me close it....
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.