The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

How do I change the parent for an issue

Mark Lemberger
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 1, 2025

I have an issue (an epic) that I need to move to a different parent issue (different initiative). In essence moving a child issue from one parent to another parent.

 

 

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

4 votes
Answer accepted
Trudy P Claspill
Community Champion
May 1, 2025

Hello @Mark Lemberger 

Welcome to the Atlassian community.

1. You can edit the Parent field in the Epic.

Screenshot 2025-05-01 at 7.28.55 AM.png

2. While viewing the Epic you can hover over its parent issue key in the breadcrumbs at the top to reveal the pencil/edit icon. Click on that for a dialog to choose a different parent.

Screenshot 2025-05-01 at 7.29.55 AM.png

3. In a Plan that shows the Epic and its parent along with other qualifying parent issue types, you can drag and drop the Epic from its current parent to a new parent. You then have to review your Unsaved Changes and accept that change for it to be applied back to the Epic outside of the Plan.

Mark Lemberger
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 1, 2025

Trudy, thank you! Worked as expected.