The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 
  • Community
  • Q&A
  • Jira
  • Questions
  • How do I change the Sprint Burndown Gadget to display by Story Points, Issue count, etc. (like I can for the burndown chart itself)?

How do I change the Sprint Burndown Gadget to display by Story Points, Issue count, etc. (like I can for the burndown chart itself)?

tiagosantiago
October 21, 2016

Hi,

It seems impossible to change the Sprint Burndown gadget display type. Anyone knows any trick/workaround for this ?

 

Thanks in advance!

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

4 votes
Jonas Krispin
Contributor
November 28, 2016

ran into the same question today.

  1. Go to your Board that the gadget is using
  2. "Board -> configure" on the upper right
  3. "Estimation" from the left side tabs
  4. set Time tracking to none (and obviously "Estimation statistic" to story points in case you haven't)
tiagosantiago
November 28, 2016

Hi Jonas,

 

Thanks for your answer.

However your suggestion does not fix the issue, since we actually use Time Tracking hence we cannot disable it.

 

Regards

Jonas Krispin
Contributor
November 29, 2016

Then the only thing I can think of right now would be to copy the board and use that for the gadget with different estimation configuration.