How do I change estimation type?

Emma Oude Kempers
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
December 2, 2018

I'm having problems with my project: it turned out we have been estimating our issues in storypoints while we log work in hours. This makes the workflows worthless. 

I want to estimate in hours, how can I make this work?

Jira support says: 

Go to your board, then select more > board settings.

This is nowhere to be found on my board.

1 answer

1 accepted

1 vote
Answer accepted
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
December 2, 2018

Actually, there's nothing wrong with estimating in points and logging hours.  See https://confluence.atlassian.com/jirasoftwarecloud/configuring-estimation-and-tracking-764478030.html

But, to answer the question, the tasks have the estimate field, it's just not shown.  You will need to add "time tracking" to the create, edit and view screens for the task issue type.  Also check it's not hidden in the field configuration for tasks