How do I add a swimlane to a Kanban board in JIRA based on sprint number/date?

Robert Bratton
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 28, 2015

This question is in reference to Atlassian Documentation: Configuring swimlanes

Ask your question here...

1 answer

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
October 28, 2015

Use a JQL swimlane definition and put in "sprint = X".  Pain to maintain though, as you'll need a new one for each new sprint.