I had a request to see if it is possible to use JIRA software project for vacation planning.
Currently I have created a Scrum board with Sprints being "July Vacation" "August Vacation" etc.
Is there a way of showing the Task which is 1 day within Calendar & Timeline to be only for 1 day
The Same for Timeline. Every Epic seems to be defaulted to 5 days.
Hi Sian,
Try putting in the Start date and End date (or Due date) with the same date.
Hi @Sian Snook
No if the issue spans multiple days it will be shown as so.
Mail calendars to the same if you select a period
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
But I have the task as one 1 day?
The smallers unit of time I can do on the timeline is 5days? Same for calendar?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Sian Snook
Both the board and calendar are based on dates not on estimation.
Estimation is related to time tracking.
As @John Funk mentions, set the start and due date to a single day.
The Target start and end dates are related to plans and you can't use them on a project board.