I had a request to see if it is possible to use JIRA software project for vacation planning.
Currently I have created a Scrum board with Sprints being "July Vacation" "August Vacation" etc.
Is there a way of showing the Task which is 1 day within Calendar & Timeline to be only for 1 day
The Same for Timeline. Every Epic seems to be defaulted to 5 days.
Hi Sian,
Try putting in the Start date and End date (or Due date) with the same date.
Hi @Sian Snook
No if the issue spans multiple days it will be shown as so.
Mail calendars to the same if you select a period
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
But I have the task as one 1 day?
The smallers unit of time I can do on the timeline is 5days? Same for calendar?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Sian Snook
Both the board and calendar are based on dates not on estimation.
Estimation is related to time tracking.
As @John Funk mentions, set the start and due date to a single day.
The Target start and end dates are related to plans and you can't use them on a project board.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.