I am working within a Timeline view and dealing with several Tasks, under an Epic, all under an Initiative. In the course of a project, some Tasks get delayed, and I'd like dependent Tasks to automatically shift to the right reflecting the delay. I can't seem to make this happen automatically, so with an Epic containing several Tasks, this manual process is very tedious.
How do I make the Timeline view act more like a traditional Gantt Chart where dependent tasks are automatically shifted to the right or left depending on their predecessors completion or delay?
Hello @Jason Schwartz
Welcome to the Atlassian community.
The Plans feature, available with Premium and Enterprise subscriptions, has an Auto-scheduler feature. I haven't worked with that, but I think it considers dependent/predecessor task dates when auto-scheduling.
Jira does not natively have a single-button feature already built to manage this process otherwise.
However I did write an article on how to do that with Automation Rules. Take a look at that and let me know if you have questions.
Updating dependent task's dates when predecessor task date changes