How can I put Stories and Tasks on the Timeline, without being related to Epics? Any configuration? It is possible?
The Timeline in Jira Software does require Epics to be active - without them, the Timeline won't function.
There's a few alternative options though:
Ste
hi, @Ste Wright
when you say active epic, does it mean that it has to be an in progress or done status?