The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

How can I move Team Manged Project to Community Manged Project?

Raunak Maskay
Community Champion
April 8, 2025

Currently my team mistakenly created team manged project which has limited access to reports and permission. Can i move all the tickets history from team managed project to community manged project?

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

4 votes
Answer accepted
Rebekka Heilmann _viadee_
Community Champion
April 8, 2025

Hi @Raunak Maskay 

You cannot change the project type after creation. Therefore you need to create a new Company Managed project and then bulk move all your issues into the new project.
You will see that change in the history but also any changes that happened before that, so yes, the issue history will be preserved.

Just go to the Issue search, filter for your project and then Bulk Edit > Move issues.

 

DEPLOYMENT TYPE