I’m using portfolio 3.1.0.
I have plan with Stories and sub-task. Some of the Stories and sub-task have assignees in Jira some not.
My issue: Using the “Calculate” function, the assignee from Jira is not kept in my plan. For some of the already assigned issues portfolio assigns other team members.
I expected, that all not assigned issues get a proposed assignee, but the already assigned resources will be kept.
The current behavior ends up in the situation, that after each calculation my previous assignments are lost, or changed by portflolio.
If I manually assign the issues in portfolio, this is stable over several calculations. But after a commit to Jira it is lost again.
How can I force portfolio to keep the assignees from Jira?