Hello everyone,
I have a problem with my guideline line : we did our Sprint Planning last Tuesday, and selected the stories for this sprint.
But we created the Sprint in Jira only yesterday (my bad), while giving it a starting date on Tuesday. Which gives us the following BurnDown :
As you can see, the story points only appears on the second day. I can deal with that, even if it is not the best.
But the guideline follows the abscissa, instead of giving us the real guideline.
It is logical, because the Sprint was created yesterday, making the story points appear on it only yesterday too, making it so that on Tuesday, there was 0 point.
Do you have a way to correct that, please ? For example, a way to force the original estimation to start on Tuesday instead of Wednesday ?
Thank you !