The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

How can I change the progress?

Equipe Versátil
April 15, 2014

Some issues obey the "remaining estimate" / "original estimate" and others don't.

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
April 15, 2014

Sorry, that doesn't really have enough information to explain what your actual problem is.

It's clear some issues behave according to some pattern, and others do not, but "the remaining estimate / original estimate" is only part of a description of the pattern you mean. I can't begin to guess what you're talking about, other than it's related to the estimate fields.

I think you need to explain more - what does "the "remaining estimate" / "original estimate" " actually mean? What issues are behaving and what are the others doing differently? What are the differences between working and broken issues?

Equipe Versátil
April 15, 2014

Hi Nic.

Sorry I didn't make myself clear.

The problem is with Gantt Charts on Demand. I have some issues that show progress and I have others that don't. All of them have the fields Original Estimate and Remaining Estimate filled, bus only some of them calculate the % of Progress.

The other problem I'm facing is that when I change the start date and I refresh the chart, the date goes back to the old one. How can I fix it?

Thank you..
Fernanda

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
April 16, 2014

Ok, so, what are the differences between an issue that works and one that does not?

I think the date thing is a bug, but I'm not sure (and I don't see it in the OnDemand I've got access to)