How are days in column calculated on the kanban Board?

RL
February 11, 2026

Does the day increase as the issue hits 24 hours old or does it flip at 00:00?

I suppose I could create a dummy issue and watch.

1 answer

2 votes
Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
February 11, 2026

Hi @RL 

I recall the "days in column" feature sums the total time a work item is in a column based upon the changelog history.  Thus, it adds up the time and divides by a 24 hour day.  This time could include a work item being in a column, leaving it, and returning again later.

Kind regards,
Bill