Viraj Dubey October 17, 2024

 

Hello i want to change the JIRA structure of all my projects. 
All the projects are Team and Company Managed  i need a step by step guide to do so.

If structure of Team managed projects cannot be changed please guide me with how can i change them all into Company managed at once.


Thanks 

2 answers

Viraj Dubey October 18, 2024

Thank you so much!!

 

3 votes
John Funk
Community Champion
October 18, 2024

Hi Viraj - Welcome to the Atlassian Community!

I am assuming you are talking about the Issue Type Hierarchy and not the Structure add-on app. 

You must be a Jira Administrator to change it. Go to Settings > Issues > Issue Type Hierarchy. There you can make the change. This will only apply to Company-managed projects. Team-managed projects cannot be changed - the top level is Epic. 

Viraj Dubey October 18, 2024

Yes exactly Issue Type Hierarchy !!! 

Thanks a lot will try these steps 

 

Like John Funk likes this
John Funk
Community Champion
October 18, 2024

You are welcome - Good Luck!