I found an inconsistency in showing Estimate and Remaining time in GreenHopper planning board on tasks having sub-tasks. I'm not sure whether it's a feature or a bug, but to me the behaviour is wrong and very inconvenient.
If a task has sub-tasks, Estimate field in GreenHopper shows time without sub-tasks time, but Remaining - with sub-tasks time. On Epic it shows Original Time Estimate without sub-tasks included in the tasks.
So, Estimate on Task with sub-tasks differs from Remaining.
Original Time Estimate on Epic with such task is wrong (without sub-tasks time).
Could you please advcie is there a work-around to have Original Time Estimate on Epic and Estimate on task with sub-tasks reflected correctly?
Community moderators have prevented the ability to post new answers.
Hey there, Azat.
Check on the following explanation regarding the issue that you having here. Perhaps it will be able to shed some light:
https://answers.atlassian.com/questions/84349/rapid-board-time-estimates-with-sub-tasks?page=1#84605
Warm regards,
Danial