Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Estimation at different hierarchical levels

slucchesini
Contributor
November 21, 2025

Hello,

I'm trying to implement something in Plans and I'd like the community advice on best practices.

Basically, we want to estimate our projects at different levels: Initiative, Epic and Story, and check if it matches. By matching, I mean that the sum of estimates in Epic should ideally be the same as the estimate on their parent Initiative, and so on. We would also like to be able to make reports on that, e.g take the mean difference between the direct-estimate and the sum-of-children-estimate for example.

For now we're populating 3 different fields with Automations:

  • A0 is the direct estimated value on Initiatives
  • A1 is the direct estimated value on Epics, and is the sum of children-epics-A1-values on Initatives
  • A2 is the direct estimated value on Stories, the sum of children-stories-A2-values on Epics the sum of children-epics-B2-values on Initatives

As you can tell, it's kind of complicated and I'm not a big fan.

I know that Structure would offer a more flexible way to do this but then the result wouldn't appear on the Work item view and it may be a problem for us. I don't know about what BigPicture offers.

What are the industry's best practice in this regard? Do you think it can prove useful or is this totally irrelevant? Should we consider a different approach?

Thanks!

Simon

1 answer

0 votes
Marc -Devoteam-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 21, 2025

Hi @slucchesini 

In my opinion estimations are not don on levels above story.

Work types aboe story are based on time realtion in my point of view.

An Epic should be based on a time fram from 1 to 3 months, An Initiative for up to a year or a little over.

Work type beneath Epic are in a Sprit and a sprint has a duration and the team acting on the sprint has a capacity, the capacity has an avarage value of sotry points.

This what the team can accomplish, in a sprint.

You can do a roolup of the estimations on Epic level and on Initiative level with automations, but you should not estimate theses levels.

slucchesini
Contributor
November 21, 2025

Thanks for your insights! I get your approach but then how do you come up with a project's budget? Do you make it totally independant of the estimate time spent?

Marc -Devoteam-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 21, 2025

Hi @slucchesini 

Yes.

When a project is confimed, creating stories to provide the work to the teams, estimaitons can change while the project is realized.

Are you saying you already created all stories and Epics with estimations before the project is stated adn you use this as budget?

slucchesini
Contributor
November 21, 2025

No, but we try to make it match more or less. We tend to think that a project will last e.g one year with 5 people / week so that makes 260 MD, and then when we split the work into stories we try to compare to see if we had a good estimate of the workforce needed.

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
ENTERPRISE
PERMISSIONS LEVEL
Product Admin Site Admin
TAGS
AUG Leaders

Atlassian Community Events